Please note that all connections to the NOTL Hydro grid must be parallel and the cost of a single phase bi-directional meter will be approximately $110.
|
|
We will respond with the pre-FIT consultation information as soon as possible. Please note that FIT projects must pass an OPA screening prior to Niagara-on-the-Lake Hydro proceeding with a Connection Impact Assessment (CIA). CIA fees are as follows:
|
| |
|
|
| |
|
CAE projects <= 500kW $3500.00
Non-CAE projects <= 1mW $5000.00
Non-CAE projects > 1mW $7000.00
*Charges in Canadian dollars, subject to HST.
|
| |
|
There is a monthly FIT/MicroFIT service charge of $5.25 (plus HST)
|
|
An APPLICATION TO CONNECT to Niagara-on-the-Lake Hydro's Distribution System is required for all FIT/microFIT projects. Please complete APPLICATION TO CONNECT and return it to Niagara-on-the-Lake Hydro via one of the following methods:
|
|
Drop-Off at NOTL Hydro Office
NOTL Hydro
8 Henegan Road
Virgil ON, L0S 1T0
|
|
.jpg) |
|
Mail to NOTL Hydro Office
(address above, PO Box 460)
|
|
|
Fax application to:
NOTL Hydro at (905)468-3861
ATTN: Kevin Sidey |
|
 |
|
Email copy of application to:
Kevin Sidey - Senior Engineering Technologist
|
|
|