Please note that all connections to the NOTL Hydro grid must be parallel and the cost of a single phase bi-directional meter will be approximately $110.

 
Please note that FIT projects must pass an OPA screening prior to Niagara-on-the-Lake Hydro proceeding with a Connection Impact Assessment (CIA).  CIA fees are as follows:
     
   
Projects <= 500kW       $3,500.00
Projects <= 1mW          $5,000.00
Projects > 1mW            $7,000.00
 
*Charges in Canadian dollars, subject to HST.
 
 
There is a monthly FIT/MicroFIT service charge of $5.25 (plus HST)
An APPLICATION TO CONNECT to Niagara-on-the-Lake Hydro's Distribution System is required for all FIT/microFIT projects.  Please complete APPLICATION TO CONNECT and return it to Niagara-on-the-Lake Hydro via one of the following methods:
  
Drop-Off at NOTL Hydro Office       
NOTL Hydro                                          
8 Henegan Road
Virgil ON, L0S 1T0
   
 
Mail to NOTL Hydro Office
(address above, PO Box 460)
 
Fax application to:
NOTL Hydro at (905)468-3861                      
ATTN: Kevin Sidey
    
Email copy of application to:
Kevin Sidey - Senior Engineering Technologist
   